§ 17.14.030. Filing requirements—Completeness.  


Latest version.
  • A.

    Applications for the approval of a tentative map shall be filed with the director of planning.

    B.

    When an application for a land division is first received, it shall be reviewed for completeness as to form and content by the planning director and, if not complete, the planning director shall notify the applicant in writing as to what must be done to make the application complete within thirty days from the date the application was originally submitted. A redetermination as to whether the required information has been submitted and therefore the application is complete shall occur within ten working days of the date the additional information is submitted by the applicant. The applicant shall be notified of the determination.

    C.

    Once all information required to complete the review of the tentative map is provided, the director of planning shall accept the application for the tentative map as complete.

(Ord. 981 § 18, 1991; Ord. 854 § 2 (part), 1987: prior code § 11623)