§ 17.40.020. Required inspections designated—Notice to county.  


Latest version.
  • The director of planning shall make such inspections as deemed necessary and shall be notified twenty-four hours in advance of any required inspection. Minimum inspection requirements follow:

    A.

    The inspection of clearing and grubbing work before grading operations are started in any cut or fill area;

    B.

    The inspection and compaction testing of subgrade before the placing of subbase, base and surfacing;

    C.

    The inspection of storm drain and sewer pipe installation and backfill, including compaction testing;

    D.

    The inspection and compaction testing of subbase and base prior to paving;

    E.

    The inspection of all penetration treatment, seal coat, and paving while the work is in progress;

    F.

    The inspection of concrete forms;

    G.

    The inspection of concrete while being placed;

    H.

    Final inspection.

    (Ord. 854 § 2 (part), 1987: prior code § 11676.2)

(Ord. No. 1379, § 128, 1-29-2013)